Work Plan
Kootenay Lake BCWS Crews
July 6, 2026
Central Windthrow Area
Now complete - great work
Back-End Corridors
Crews will continue to work these corridors to completion.
Chipping material dragged to main trail and staged at 45 degrees.
Firewood piled for retrieval with dump trailer or UTV.
Waste material moved to A) Areas where dump trailer can reach or B) into burn piles.
Piling for burning should be reserved for back-end areas where yarding / winching / loading is not practical.
Main Landing Area
It is time to begin to make this area look better.
Loki crews will chip some material off the top.
Waste material to be chucked aside for loading and hauling away.
Firewood to be mixed into loads with the better quality stuff coming from back 40.
Falling Crew
BCWS or Loki Faller pair to work west-most area for DTA, wind-throw, and bucking to longer lengths
Prepare area for continued corridor work